PHASE 1-1 zeit RIVER COUNTY 1 CONSTRUCTION PROGRESS IN MAY & JUNE 2022
VGSI engineers are also building the rough parts of townhouses and villas. Clubhouse A31 utility area has completed the construction and is in the construction phase of roofing and tiling.
Clubhouse A32 is under construction of the ground floor structure, expected to be completed in the next few months.
The park along the riverside has been completed and installed on the ground and is being built for internal walkways, water supply, drainage, and lighting systems before entering the construction phase to complete the landscape in the next few months.
Model House of Semi-Detached Villa: has built the rough part of the house wall, balcony, gate, and fence. Currently, the model house is under construction of exterior ceiling/ceiling outside and external painting/painting outdoors.
Model House Single Villa: Completed the construction of a rough house. Next, workers will carry out exterior decoration works such as painting walls and constructing gates and fences.
Model House Shophouse: has completed the rough foundation, walls on the ground floor, and two floors. In April, the engineering team is expected to complete the exterior and interior decoration.
Model House Townhouse: completed construction of the brick wall. Next, the finishing step will take to complete the exterior wall priming, tile roofing, and waterproofing of the floor and roof… At the same time, the workers will also carry out the construction of the exterior exteriors such as the balcony exit door, entrances, windows, main gates, and fences.

Almost the unit houses are constructed in order to complete the schedule in early 2023 – Photo VGSI

A part street view of the Semi-detached Villa in the outside completion – Photo VGSI
Relate Project Status
As of October 2022, the Zeit River County 1 project has completed the construction of townhouses, shophouses, semi-detached villas, and…
read moreShophouses, Townhouses, Single Villas & Semi-Detached Villas have completed the rough part and finished roofing and painting. The riverside villa…
read moreModel House of Semi-Detached Villa: has built the rough part of the house wall, balcony, gate, and fence. Currently, the…
read moreModel House of Semi-Detached Villa: has built the rough part of the house wall, balcony, gate and fence. Currently, the…
read moreAs of February 2022, the Zeit River County 1 project has completed basic infrastructure, roads and trees, internal sidewalks, and…
read moreAs of November 2021, the Zeit River County 1 project has completed the following stages: basic infrastructure, electrical system, water…
read moreThe construction has paused under the direction of the People's Committee of HCM City due to the epidemic of the…
read moreThe zeit River County 1 project has completed the underground infrastructure system and internal roads until June 2021. Besides, VGSI…
read moreThe zeit River County 1 project has completed the basic facilities and riverbank region until April 2021 (drainage system, bank…
read moreThe zeit River County 1 project had completed the central ground drainage system of Phase 1-1 until Mar 2021. The…
read moreThe zeit River County 1 project had completed the central ground drainage system of Phase 1-1 until January 2021. The…
read moreThe zeit River County 1 project had completed the main ground drainage system of Phase 1-1 until December 2020. The…
read moreUntil November, 2020, Phase 1-1 zeit River County 1 has currently completed the drainage system, electric system, and ground leveling…
read moreUpdated the construction of Phase 1.1. zeit River County 1 until October 2020. Image - VGSI: The workers are rushing…
read moreUpdated the construction of Phase 1.1. zeit River County 1 until September 2020 Up to now, the project is implementing…
read moreUpdated the construction of Phase 1.1. zeit River County 1 until July,2020 Image: VGSI Image: VGSI Image: VGSI
read moreUpdated the construction of Phase 1.1 zeit River County 1 until June 2020 Image: VGSI Image: VGSI Image: VGSI
read moreUpdated the construction of Phase 1.1. zeit River County 1 until May,2020 Image: VGSI Image 2 - VGSI
read moreUpdated the construction of Phase 1.1 zeit River County 1 until April,2020 Trucks operating at the construction site and ensuring…
read moreUpdated the construction of Phase 1.1 zeit River County 1 until Mar/2020 Engineers and staff are doing exercise to save…
read moreOn February 3rd, 2020 the developer VGSI has started to development construction of phase 1.1 zeit RIVER COUNTY 1 at…
read more