PHASE 1-1 zeit RIVER COUNTY 1 CONSTRUCTION PROGRESS IN MAR 2021

The zeit River County 1 project had completed the central ground drainage system of Phase 1-1 until Mar 2021. The construction engineers completed road surface of four main roads. At the same time, the internal road system is also under construction and underground structures. The engineers also promoted the river embankment line in parallel to complete the river landscape for the project.

VGSI photo: The inter-roads are preparing for pave stage 

VGSI photo: The embankment road along Soai Rap River is underground treatment, preparing for the construction and installation of the park soon

Relate Project Status

As of October 2022, the Zeit River County 1 project has completed the construction of townhouses, shophouses, semi-detached villas, and… read more
Shophouses, Townhouses, Single Villas & Semi-Detached Villas have completed the rough part and finished roofing and painting. The riverside villa… read more
VGSI engineers are also building the rough parts of townhouses and villas. Clubhouse A31 utility area has completed the construction… read more
Model House of Semi-Detached Villa: has built the rough part of the house wall, balcony, gate, and fence. Currently, the… read more
Model House of Semi-Detached Villa: has built the rough part of the house wall, balcony, gate and fence. Currently, the… read more
As of February 2022, the Zeit River County 1 project has completed basic infrastructure, roads and trees, internal sidewalks, and… read more
As of November 2021, the Zeit River County 1 project has completed the following stages: basic infrastructure, electrical system, water… read more
The construction has paused under the direction of the People's Committee of HCM City due to the epidemic of the… read more
The zeit River County 1 project has completed the underground infrastructure system and internal roads until June 2021. Besides, VGSI… read more
The zeit River County 1 project has completed the basic facilities and riverbank region until April 2021 (drainage system, bank… read more
The zeit River County 1 project had completed the central ground drainage system of Phase 1-1 until January 2021. The… read more
The zeit River County 1 project had completed the main ground drainage system of Phase 1-1 until December 2020. The… read more
Until November, 2020, Phase 1-1 zeit River County 1 has currently completed the drainage system, electric system, and ground leveling… read more
Updated the construction of Phase 1.1. zeit River County 1 until October 2020. Image - VGSI: The workers are rushing… read more
Updated the construction of Phase 1.1. zeit River County 1 until September 2020 Up to now, the project is implementing… read more
Updated the construction of Phase 1.1. zeit River County 1 until July,2020 Image: VGSI Image: VGSI Image: VGSI read more
Updated the construction of Phase 1.1 zeit River County 1 until June 2020 Image: VGSI Image: VGSI  Image: VGSI   read more
Updated the construction of Phase 1.1. zeit River County 1 until May,2020 Image: VGSI     Image 2 - VGSI   read more
Updated the construction of Phase 1.1 zeit River County 1 until April,2020 Trucks operating at the construction site and ensuring… read more
Updated the construction of Phase 1.1 zeit River County 1 until Mar/2020 Engineers and staff are doing exercise to save… read more
On February 3rd, 2020 the developer VGSI has started to development construction of phase 1.1 zeit RIVER COUNTY 1 at… read more